EPC of Truck Loading Systems

ABM was hired to provide design, fabrication, construction and commissioning support for a truck loading facility supplying 60M3 per hour liquid propane at the Gas processing plant located at Goldboro, Nova Scotia. The project also included:

  • Design, fabrication and building of a skid based custody transfer / truck loading module including control valves, revenue metering and separation vessel.
  • Interface to Loading / Metering control system
  • Extension of new pipeline from Railcar facility to Truck Facility to accommodate increase flow rates

The engineering scope included extensive modeling of the existing plant distribution and storage systems to confirm adequate flow rates prior to sanction of the project.  Subsequent Flow / Pressure Surge modeling of the plant and facility was required to identify sources of and remediation for pressure spikes within the plant and truck loading facility.  The solution was determined to be primarily control system based updates required in valve opening / closing sequences.

  • Decommissioning Studies

    ABM has been hired to provide planning, inspection, and engineering assessment for the early concept studies...

    View More>
  • Pigging Support Services

    ABM has been involved in every Sable Offshore Energy Project pigging campaign conducted over the past 10 years.

    View More>
  • EPC of Truck Loading Systems

    ABM was hired to provide design, fabrication, construction and commissioning support for a truck loading facility...

    View More>
  • Cohasset-Panuke Decommissioning

    ABM was contracted to remove piping, structural and electrical systems, and install minimum navigational aids to the Cohasset-Panuke

    View More>
  • Life Cycle Labour Support

    ABM was contracted throughout the life of the Cohasset-Panuke oil platform to supply onshore and offshore trades labour support.

    View More>
  • Piping Fabrication & Installation

    ABM was hired to complete a campaign to upgrade from FRP piping to Cunifer and Duplex piping on two existing offshore...

    View More>
  • Flare Boom Piping Modifications

    ABM was contracted to design, fabricate and install new piping and hose connections from the flare and diverter piping system connecting...

    View More>
  • Thebaud Compression Platform Modifications

    ABM was hired by SaiWoo Contracting to complete project management, production of fabrication drawings and onshore fabrication of two pipe racks ...

    View More>
  • HVAC Assessments & Modifications

    ABM performed HVAC and refrigeration system maintenance and repairs for the Transocean owned, Henry Goodrich...

    View More>
  • 10 Year Maintenance Turnaround

    ABM completed a scheduled 21 day turnaround and 4-month maintenance campaign involving multiple maintenance support activities on...

    View More>
  • Hook-up & Commissioning of Gas Platform

    ABM was hired by Single Buoy Mooring (SBM) to complete the Hook-up and commissioning on a new offshore jack-up sour gas production and...

    View More>
  • EPC of Additional Living Quarters

    The project included the provision for use of the existing facility crane. Key steps in this provision included limiting the module weight, brown-field installation on...