EPC of Additional Living Quarters

ABM worked rigorously to:

  • Fabricate and install a 45 tonne structural support frame and the associated heavy lift plans
  • Design, procure and install the modularized A60 rated offshore accommodations block providing 139 M2 floor area including five rooms / ten beds, office, dry goods storage and exercise room
  • Design, fabricate and construction of  the utility services (HVAC, electrical power, fire & gas alarm, sprinklers, telecoms, water supply & waste) supplying the Accomodations block.

The project included the provision for use of the existing facility crane. Key steps in the execution of this project  included limiting the module weight, brown-field installation on the operating facility without interruption of the existing accommodations block and extension and modification of existing services to the new ALQ Modules. In addition, ABM provided heavy-lift design for the structural frame from shore to the supply vessel and from the supply vessel to its final in place location in close proximity to the existing structure, as well as lifting of the modularized accommodations blocks and HVAC Skid.

  • Decommissioning Studies

    ABM has been hired to provide planning, inspection, and engineering assessment for the early concept studies...

    View More>
  • Pigging Support Services

    ABM has been involved in every Sable Offshore Energy Project pigging campaign conducted over the past 10 years.

    View More>
  • EPC of Truck Loading Systems

    ABM was hired to provide design, fabrication, construction and commissioning support for a truck loading facility...

    View More>
  • Cohasset-Panuke Decommissioning

    ABM was contracted to remove piping, structural and electrical systems, and install minimum navigational aids to the Cohasset-Panuke

    View More>
  • Life Cycle Labour Support

    ABM was contracted throughout the life of the Cohasset-Panuke oil platform to supply onshore and offshore trades labour support.

    View More>
  • Piping Fabrication & Installation

    ABM was hired to complete a campaign to upgrade from FRP piping to Cunifer and Duplex piping on two existing offshore...

    View More>
  • Flare Boom Piping Modifications

    ABM was contracted to design, fabricate and install new piping and hose connections from the flare and diverter piping system connecting...

    View More>
  • Thebaud Compression Platform Modifications

    ABM was hired by SaiWoo Contracting to complete project management, production of fabrication drawings and onshore fabrication of two pipe racks ...

    View More>
  • HVAC Assessments & Modifications

    ABM performed HVAC and refrigeration system maintenance and repairs for the Transocean owned, Henry Goodrich...

    View More>
  • 10 Year Maintenance Turnaround

    ABM completed a scheduled 21 day turnaround and 4-month maintenance campaign involving multiple maintenance support activities on...

    View More>
  • Hook-up & Commissioning of Gas Platform

    ABM was hired by Single Buoy Mooring (SBM) to complete the Hook-up and commissioning on a new offshore jack-up sour gas production and...

    View More>
  • EPC of Additional Living Quarters

    The project included the provision for use of the existing facility crane. Key steps in this provision included limiting the module weight, brown-field installation on...

    View More>